
Harbour Central development includes several high-rise buildings with up to 41 floors over a 6m deep basement. Piling works included both an embedded retaining wall and piled foundations.
CLIENT Galliard HomesCONTRACTOR Galliard ConstructionENGINEER Meinhardt UKSCOPE379no. 750mm diameter CFA bearing piles 363no. 900mm diameter CFA bearing piles 608 no. 900mm diameter CFA secant wall pilesPLANTCPL 55t CFA drilling rigs 7m3 hymix concrete agitator Putzmeister 2005 concrete pump IHI CCH300T – 30 Tons capacity telescopic crawler crane
Harbour Central development includes several high-rise buildings with up to 41 floors over a 6m deep basement. Piling works included both an embedded retaining wall and piled foundations.
Given the high ground water table and the soil conditions, the appropriate solution proved to be a secant piled wall, designed as cantilever for temporary condition.
For the high compression loads transmitted to the foundation system, large diameter
CFA piles were installed, toeing into a very stiff sand layer.
The piling works for the secant wall included over 600 piles with 900mm diameter, for which a guide-wall was previously installed to ensure verticality and required overlap between the hard and soft piles.
The bearing piles included over 700 piles with diameters of 750mm and 900mm embedded into the Thanet Sand formation.
The ground conditions comprised in succession Made Ground over Alluvium, River Terrace Deposits, Lambeth Group Formation, Thanet Sand and Chalk. Groundwater was found at approximately 1.5m depth.
The thickness of the Made Ground of up to 3.5m over 2m of Alluvium, high ground water table and limited lateral deflection criteria justify the use of 900mm piles for the secant piled wall.
As the Thanet Sand was found at relatively shallow depth, between 15m to 18m depth, is was justified to take the bearing piles into this layer, obtaining high bearing capacities of up to 5500kN.
For the secant piled wall 900mm diameter continuous flight auger (CFA) piles were placed at 700mm centres through a guide wall, to a depth of 13m. To ensure that a ground water seal was created the soft piles were installed to 10m depth, ensuring they are below the deepest excavation level and into a cohesive layer.
Following a pre-design based on subgrade reaction modulus method, to further evaluate the lateral displacements of the secant piled wall, a finite element analysis was performed using specialized geotechnical software Plaxis.
This allowed for a more accurate assessment of the wall movements, as on some areas of the basement the maximum retained height reached 7m.
The piled foundation solution was value engineered, managing the reduce the pile diameters from 1050mm and 900mm to 900mm and 750mm respectively, obtaining a significant saving both in terms of costs and time for the piling works.
The design was conducted in accordance to the Eurocodes, performing load tests on both preliminary and working piles to confirm and validate the design.
Case Studies
Central Piling has completed a piling contract to enable essential homes to be built for residents in Tilbury, Essex.
Case Studies
Central Piling has completed a major piling contract that is enabling King’s College London to build new high quality student accommodation in southeast London.
Case Studies
Central Piling enabled construction to begin on a major regeneration scheme that will bring much-needed housing and amenities to a former industrial area in Luton.
Case Studies
Central Piling has played an important role in helping one of the UK’s leading housing companies regenerate a former industrial site for much-needed housing and amenities. The Hyde in north London is a landmark development of 387 homes (including 139 shared ownership and 34 affordable rent) and 647m2 of community facilities and commercial space.
Case Studies
As part of the redevelopment of Galliard Homes a new residential Development is to be developed.
Case Studies
The client required a basement to be constructed as part of the works at Barking Road. To enable this it was considered that, due to the high ground water table, a secant piled wall was the best solution.
Case Studies
The challenge of this project was to form a double basement underneath and to the rear of this listed building in order that a swimming pool and gym area could be provided. Access for all equipment was restricted to 1.8m width and in some areas 2.5m in height.
Case Studies
The challenge of this project was to form greater/larger space within a confined space in a listed building to provide banking financial services. Access for all equipment was restricted to 1.8m width and in some areas 3.5m in height.
Case Studies
Piles were required for abutments for a new bridge across the river Blakewater in the northwest of England.
Case Studies
As part of the redevelopment of Epsom Downs Racecourse a new grandstand is to be constructed.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |