Piling innovation rises to a technical challenge
Central Piling is using two continuous-flight auger (CFA) piling rigs to install deep foundations on a former quarry site in Kent.
Central Piling is using two continuous-flight auger (CFA) piling rigs to install deep foundations on a former quarry site in Kent.
The project is the latest phase of a major residential development on behalf of the Erith Hills LLP, made up of Anderson and L&Q, comprising 849 new homes, a new primary school and a 12-acre ecology park.
Called, appropriately enough, The Quarry, the scheme occupies a disused 50-acre quarry in Erith that had lain untouched for more than 30 years.
Central Piling has been working on-site since 2021, installing piles to support the new development. Due to the nature of the site, the ground conditions are highly variable, with large areas of mixed fill reaching depths of up to 30m in some places.
The challenge here is to install piles that are deep enough to reach firm ground – and that means piles up to 40m deep.
“Rotary piling wasn’t feasible due to the depth of casing required and driven piling might not have penetrated harder elements within the fill,” says Central Piling managing director Steve Hadley.
Instead, Central Piling chose to use CFA piling techniques. But that gave rise to another challenge: few CFA piling rigs can drill down beyond 30m. “There are rigs that can drill to about 36m but they are huge, 120-tonne machines,” explains Steve.
Central Piling has overcome this problem by deploying two piling rigs, working in tandem. Both are Italian-made Soilmec machines: an SF50 CFA rig and its larger stablemate, the SF65 rig.
The larger of the two rigs is used to install the first stage of the pile. “This is the main machine,” says Steve. “It can drill down to 29.5m”.
Once the SF65 has drilled to about 24m, it decouples and backs away to allow the smaller SF50 to position itself over the first auger, to which it couples its own auger. This machine then continues the boring process to reach the required depth.
“This presented a safer and higher-production solution than adding single 6m sections of auger to a single rig,” explains Steve.
Nevertheless, to make this system work, Central Piling had to develop a special tool for supporting the drilling tools as the rigs were swapped during the concreting stage of the operation. The team also configured the drum and pump set-up with a valve that allowed concrete to be shared between the two machines.
Even if a 120-tonne rig had been available, Steve doubts it would have proved suitable for this site. “It’s quite tight in some places but having two machines that can move independently means we can get into those spaces,” he says.
“I’ve never heard of anybody using two rigs in tandem like this – as far as I know, it’s a first,” Steve adds.
Piling in such ground inevitably means encountering unforeseen conditions. “We did encounter some locations of deeper fill as well as some voids,” says Steve. “This necessitated close inspection of the arisings and a suitable adjustment to the design length [of the pile].”
When such conditions arose, Central Piling had to adapt its procedure – for example, by altering extraction rates to maintain concrete pressure, and pumping additional concrete to fill voids, to ensure successful results. “In some places we had to re-drill in order to install viable piles,” says Steve. “Of course, our client understood the variability inherent on this site and were accommodating to these changes”.

Steve Hadley
Managing Director
RELATED NEWS
Central Piling MD breaks ground with Ground Engineering
May 25, 2023
Steve has now notched up more than 21 episodes as host of the “Breaking Ground” podcasts dubbed…
0 Comments4 Minutes
Our action on UN Sustainable Development Goals
January 20, 2023
We are now taking the opportunity to explain the activities we engage in that reflect some of the…
0 Comments1 Minutes
The Ground Forum’s mentoring scheme reaches dizzy heights
September 29, 2022
An organisation chaired by Central Piling MD Steve Hadley, who also chaired the FPS (Federation of…
0 Comments2 Minutes
Central Piling MD talks compassion in leadership
April 22, 2021
Seeing yourself as a brand and identifying how you want to be seen by others, are fundamental…
0 Comments3 Minutes
Future ICE President talks green with Central Piling MD
April 22, 2021
Changing the civil engineering industry to benefit both planet and people cannot be achieved…
0 Comments2 Minutes
A preview of the FPS’ 2021
March 24, 2021
The mental health and wellbeing of people in the piling industry will continue to be a focus for…
0 Comments2 Minutes
Central Piling starts 2021 with a quadruplet of contract wins
January 11, 2021
Contract wins worth over £2.6 million take the contractor happily into the New Year. Specialist…
0 Comments2 Minutes
Central Piling wins Investors in People
January 4, 2021
Central Piling has won the prestigious Investors in People accreditation. And far from resting on…
0 Comments1 Minutes
Ruby Waxes lyrical about mental health
November 16, 2020
Since becoming chair of the FPS (Federation of Piling Specialists), Central Piling MD Steve Hadley…
0 Comments2 Minutes
Confronting racial discrimination
June 5, 2020
Following his appointment as chair of the FPS (Federation of Piling Specialists) earlier this year,…
0 Comments5 Minutes