The complexity of the project called for a collaborative approach and Central Piling worked with the client and  all parties during the early design stages to enable a value-engineered solution which delivered the project on time and within budget.

The development comprised three blocks: Block A, which consisted of a new structure tied into the retained original Edwardian façade; Block B, which incorporated a single-storey retained façade with a modern zinc-clad structure above, and Block C which was probably the most challenging – a new-build over a deep basement.

Ground Conditions

The ground conditions comprised 2m of made ground over 2m of sand and gravel with sandy clay pockets occurring throughout and firm-to-stiff clay below.

Challenges

The works were scheduled to be done in phases and Central Piling used five different rigs, ranging in size from 15 tonnes to 80 tonnes, to undertake the piling works.
The geotechnical works included the installation of several embedded retaining walls formed of CFA piles in diameters from 350mm to 750mm. The most challenging geotechnical task was the installation of the embedded retaining wall for Block C, designed to facilitate the construction of a 14m-deep basement.

The complexity of the Block C retaining wall design and installation demanded a highly collaborative approach and Central Piling’s design team worked closely with the main contractor and all parties during the pre-construction design phase which was essential to the successful delivery of the project.

To ensure they achieved completion within the allotted timescale, they worked to a target of six piles per day – a considerable challenge on a site where numerous trades were working simultaneously, and so concrete deliveries had to be precisely scheduled so they could meet their target.

Solution

The most appropriate solution for the Block C basement retaining wall was determined as a propped contiguous piled wall comprising 210 CFA piles, each 750mm in diameter, installed to a depth of 20m.
The embedded retaining wall design tested the CFA piling rigs’ capabilities with the requirement to install 20m fully-reinforced piles. A special concrete mix had to be developed that would facilitate the installation of the long reinforcing cages.

Using specialised Plaxis 3D software, a three-dimensional model was built of the geotechnical structures. This incorporated not just the new Islington Square sub-structures but also the foundations of neighbouring buildings including the Almeida Theatre. The 3D model enabled inspection of the likely foundation settlement. This was followed-up by a more detailed analysis of the impact of ground movements by Card Geotechnics.

Redundancy was built into the design of the contiguous piled retaining wall to compensate for piling deviation beyond tolerance. The allowable vertical deviation for CFA piles, according to the codes of practice, is 1 in 75. For a 20m-deep pile, this would amount to roughly 260mm of possible deviation for each pile, leading to a high risk of pile clashing. The redundancy built into the wall design accommodated the possibility of omitting a pile in the event of a clash without compromising the performance of the retaining wall.

By providing Groundforce, who supplied the propping solution, with essential information regarding lateral loads, Central Piling ensured the layout of the props was optimised right at the tender stage.
Despite the complexity of the geotechnical element, all the piling was completed successfully within the scheduled programme.


ISLINGTON SQUARE, ISLINGTON,NORTH LONDON PROJECT SHEET


RELATED CASE STUDIES

Contact us

Any questions? Feel free to come in for a chat anytime

Rawden Enterprise Park,
Sixth Avenue,
Halstead,
Essex  CO9 2FL

01787 474000

info@centralpiling.com

JOIN OUR NEWSLETTER


Copyright Central Piling 2018 | Website Design by Dinc Creative

Privacy Preference Center