Piles were required for abutments for a new bridge across the river Blakewater in the northwest of England.
CLIENT Blackburn with Darwen B.C.CONTRACTOR Eurovia Infrastructure LimitedENGINEER Capita InfrastructureSCOPE 24no. 600mm Diameter CFA Bearing Piles to 18m depthPLANTSoilmec SF-50 40t Drilling Rig Concrete pump and agitator
The high loads including horizontal forces meant that piles were required. The design was carried out and allowed for by Consulting Engineers Capita Infrastructure.
The ignored depth/made ground to 6.5m underlined by stiff the very stiff clays to 18m.
Pile diameters for this project are 600mm & pile depths were 18m as requested with reinforcement for the piles 6H25x10.5m in a H12 helical. Concrete was C35/45, DC-2. The logistical planning for this contract called for an initial mobilisation to site for the first bridge abutment to be piled. Once this was complete ancillary plant to the piling rig was transported by hiab lorries to the other bridge abutment. However the rig tracked some 60m through an alternate traffic managed route to the other-side of the Blakewater river to install piles for the other bridge abutment. The movement plan below shows our course of action.
Case Studies
Central Piling has completed a piling contract to enable essential homes to be built for residents in Tilbury, Essex.
Case Studies
Central Piling has completed a major piling contract that is enabling King’s College London to build new high quality student accommodation in southeast London.
Case Studies
Central Piling enabled construction to begin on a major regeneration scheme that will bring much-needed housing and amenities to a former industrial area in Luton.
Case Studies
Central Piling has played an important role in helping one of the UK’s leading housing companies regenerate a former industrial site for much-needed housing and amenities. The Hyde in north London is a landmark development of 387 homes (including 139 shared ownership and 34 affordable rent) and 647m2 of community facilities and commercial space.
Case Studies
As part of the redevelopment of Galliard Homes a new residential Development is to be developed.
Case Studies
The client required a basement to be constructed as part of the works at Barking Road. To enable this it was considered that, due to the high ground water table, a secant piled wall was the best solution.
Case Studies
The challenge of this project was to form a double basement underneath and to the rear of this listed building in order that a swimming pool and gym area could be provided. Access for all equipment was restricted to 1.8m width and in some areas 2.5m in height.
Case Studies
The challenge of this project was to form greater/larger space within a confined space in a listed building to provide banking financial services. Access for all equipment was restricted to 1.8m width and in some areas 3.5m in height.
Case Studies
As part of the redevelopment of Epsom Downs Racecourse a new grandstand is to be constructed.
Case Studies
Crossrail required large diameter bearing piles in restricted access adjacent to the Stepney Green Shaft which provides ventilation to the underlying tunnel approximately 30m below ground level.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |