
Central Piling enabled construction to begin on a major regeneration scheme that will bring much-needed housing and amenities to a former industrial area in Luton.
CLIENTStrawberry Star HomesCONTRACTORJJ Rhatigan & Co Building ContractorsENGINEERForm SDSCOPE687no, 350mm and 177no450mm diameter CFA piles to 21.5m depthPLANTSoilmec SR-75 CFA rig
The £300 million scheme is being built on a 6.9 acre site formerly occupied by Vauxhall Motors. It is being built in four phases, with the new apartments being built first.
Phase one includes three residential towers up to 11storeys high sitting above ground floor retail units, along with a multi storey car park, communal gardens and the central park. Offices, commercial space and the hotel will be built in later phases.
Phase one contractor JJ Rhatigan appointed Central Piling to install the bored piled foundations for the three residential towers, Blocks A, B and C, which are nine, 10 and 11 storeys high respectively. In addition, Central Piling has installed a contiguous piled retaining wall to create the podium level. The piling works were carefully coordinated with those of the main contractor following behind in order to achieve the project deadline.
The variable ground consists of made ground above a thin layer of clay that contains flint, with an underlying chalk bedrock.
A detailed geo-environmental assessment of the site indicated that, due to the natural weak soils, a traditional shallow foundation would not be feasible for the high-rise nature of the new structures, and a contiguous piled foundation solution was recommended.
Central Piling carried out the pile design for both the residential tower foundations and the 250m long retaining wall, which was designed to facilitate the construction of the podium and ground level on what was a naturally sloping site.
The pile loads ranged from 50kN to 1700kN, with all piles designed to embed into the underlying chalk as competent bearing strata. The maximum pile length was 21.5m.
There is an underlying aquifer on the site, which could have become contaminated if traditional intrusive piling techniques were used. Instead, Central Piling opted for continuous flight augered (CFA) piling, as it generates minimal disturbance to the soil.
CFA is a fast and reliable method of pile installation that also has reduced impact on the environment in terms of noise and vibration.
Central Piling carried out the £500,000 piling contract in a single two month visit between July and September 2019. The first priority was construction of the embedded retaining wall, which was formed of 177, 450mm diameter CFA piles. This was followed by the installation of the 687, 350mm diameter CFA bored bearing piles for the residential tower foundations.
All the piling was carried out using a Soilmec SR-75 CFA rig – the largest rig in Central Piling’s fleet.
The main challenge was piling on a site that had different ground levels to compensate for the natural slope. This required a well-organised sequence of works, making use of ramps and temporary berms.
The piling works also had to be carefully coordinated with those of the main contractor, which had to follow immediately behind in order to meet the project deadline.
Using its most powerful rig on the contract enabled Central Piling to meet – and even exceed – the daily targets, despite the variable ground conditions.
Case Studies
Central Piling has completed a piling contract to enable essential homes to be built for residents in Tilbury, Essex.
Case Studies
Central Piling has completed a major piling contract that is enabling King’s College London to build new high quality student accommodation in southeast London.
Case Studies
Central Piling has played an important role in helping one of the UK’s leading housing companies regenerate a former industrial site for much-needed housing and amenities. The Hyde in north London is a landmark development of 387 homes (including 139 shared ownership and 34 affordable rent) and 647m2 of community facilities and commercial space.
Case Studies
As part of the redevelopment of Galliard Homes a new residential Development is to be developed.
Case Studies
The client required a basement to be constructed as part of the works at Barking Road. To enable this it was considered that, due to the high ground water table, a secant piled wall was the best solution.
Case Studies
The challenge of this project was to form a double basement underneath and to the rear of this listed building in order that a swimming pool and gym area could be provided. Access for all equipment was restricted to 1.8m width and in some areas 2.5m in height.
Case Studies
The challenge of this project was to form greater/larger space within a confined space in a listed building to provide banking financial services. Access for all equipment was restricted to 1.8m width and in some areas 3.5m in height.
Case Studies
Piles were required for abutments for a new bridge across the river Blakewater in the northwest of England.
Case Studies
As part of the redevelopment of Epsom Downs Racecourse a new grandstand is to be constructed.
Case Studies
Crossrail required large diameter bearing piles in restricted access adjacent to the Stepney Green Shaft which provides ventilation to the underlying tunnel approximately 30m below ground level.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |